Mallinckrodt Chemical Co. Destrehan St. Plant
Home / Areas of Practice / Energy Employees Occupational Illness Compensation Program Act (EEOICPA) / EEOICPA: SEC Sites By State / Mallinckrodt Chemical Co. Destrehan St. Plant
Also Known As: St. Louis Downtown Site, Mallinckrodt Chemical Works, MCW
State: Missouri
Location: St. Louis
Time Period: DOE 1942-1962; 1995 (remediation)
Facility Type: Department of Energy
Facility Description
From 1942 to 1957, Mallinckrodt Chemical Company conducted a variety of milling and recovery operations with uraniumchemical compounds at the St. Louis Downtown Site, also known as the Destrehan Street Plant. The plant refined uranium ore, ultimately producing uranium metal. The activities supported research, development, and production programs for the national defense program. By 1957, the Mallinckrodt Chemical Company had processed more than 45,000 metric tons (50,000 tons) of natural uranium products at its facilities. During closeout of operations in 1957, government-owned buildings were either dismantled or transferred to Mallinckrodt as part of a settlement. Decontamination work continued to 1962 when the plant was released back to Mallinckrodt.
This listing of the Mallinckrodt Chemical Works (MCW), is intended to cover the entire area bounded in part by North* Broadway, Angelroot Street, and Salisbury Street. Destrehan Street runs through the middle of the entire area and is a common way to reference the plant, but is by no means the only valid building address. Many buildings are also on Mallinckrodt Street. Coverage includes, but is not limited, to the Main Plant, Plant 4, Plant 6, Plant 6e and Plant 7.
Throughout the course of its operations, the potential for beryllium exposure existed at this site.
*The original address for some buildings would have been Broadway Street. Today, these same buildings have the address of North Broadway Street.
Listing
Mallinckrodt Chemical Co. Destrehan St. Plant is listed as a Department of Energy (DOE) site under the EEOICPA.
Special Exposure Cohort (SEC) Classes
Mallinckrodt Chemical Works, Destrehan Street Facility (1942-1948)–Employees of the DOE or DOE contractors or subcontractors employed by the Uranium Division of Mallinckrodt Chemical Works, Destrehan Street Facility, during the period from 1942 through 1948 and who were employed for a number of work days aggregating at least 250 work days either solely under this employment or in combination with work days within the parameters (excluding aggregate work day requirements) established for other classes of employees included in the SEC
Mallinckrodt Chemical Works, Destrehan Street Facility (1949-1957)–Department of Energy (DOE) employees or DOE contractor or subcontractor employees who worked in the Uranium Division at the Destrehan Street Facility of Mallinckrodt Chemical Works from 1949 to 1957 and who were employed for a number of work days aggregating at least 250 work days either solely under this employment or in combination with work days within the parameters (excluding aggregate work day requirements) established for other classes of employees included in the SEC
Mallinckrodt Chemical Works, Destrehan Street Facility (1958)–All employees of DOE, its predecessor agencies, and their contractors and subcontractors who worked in the Uranium Division at the Mallinckrodt Chemical Co., Destrehan Street Plant in St. Louis, Missouri, from January 1, 1958 to December 31, 1958, for a number of work days aggregating at least 250 work days, occurring either solely under this employment or in combination with work days within the parameters established for one or more other classes of employees included in the SEC
Compensation
As of 08/10/2015, the total compensation paid under Parts B and E of the EEOICPA, including medical compensation, for workers suffering from the effects of having worked at the Mallinckrodt Chemical Co., Destrehan St. Plant is $106,706,053.
Mallinckrodt Chemical, St. Louis Airport Storage Site (SLAPS) and Tyson Valley Powder Farm Workers
Did you, your spouse, or your parent become ill after working at Mallinckrodt Chemical, St. Louis Airport Storage Site (Slaps), or Tyson Valley Powder Farm? You may be entitled to up to $400,000 from the United States. For more information, call Attorney Hugh Stephens at (800) 548-4494, whether or not you have already filed a claim and even if your claim has been accepted or denied.
We assist with claims, dose reconstructions, objections, hearings, reopenings, consequential conditions, impairment ratings, wage loss, health care, home care and appeals to Federal Court. No Recovery-No Fee. 2% contingent fee for initial claims/10% for objections. 2495 Main St., Buffalo, NY 14214.
History
These properties were formerly used in the fabrication of purified uranium compounds and metals from uranium feed materials. All work was carried out under contract with the U.S. Government.
Mallinckrodt’s work at plants in St. Louis began in 1942 and continued through 1957, at which time the facilities were shut down for decontamination. This history includes only the work carried out atplants in the St. Louis, Missouri, area and as such does not cover work at Weldon Springs or at other facilities.
The initial contract work consisted of the production of uranium trioxide (U03) and uranium dioxide (UO2) to be used in the nuclear pile that was currently being constructed in Chicago. Impure natural feed material containing,low levels of uranium was processed to yield a concentrate of uranium trioxide that could be used for a reactor core. In addition, extra steps allowed the production of uranium dioxide (UO2)and uranium tetrafluoride (UF4). Uranium derby metal also was produced and then vacuum recast to form ingot metal. All of the initial contract work appears to involve 238U, with no process existing for the purification and working of 232Th, highly enriched uranium, UF6, fission products, or by-product material (Fig. 2).
A variety of work processes was carried on at various times during the period 1942 to 1966 including: (1) machining of natural uranium metal rods to make reactor fuel slugs, (2) reverting UF4 to UO2 or to U3O8, (3) recovering scrap uranium metal, (4) producing U02F2, (5) extracting and concentrating 230Th from pitchblende raffinate, and(6) experimentally purifying or reworking very low enrichment UF4.
Work was carried on to extract uranium from pitchblende ore and to concentrate this extract. In addition, 226Ra and its daughters were extracted, along with the lead content, since the African Metals Company retained ownership of the radium content of the ore. The radium and lead were precipitated when the pitchblende after dissolution in nitric acid was combined with sulfuric acid. This precipitate was sent to the Lake Ontario Ordnance Works, Lewiston, New York, for storage. Much of this material was moved to facilities operated by National Lead of Ohio, Fernald, Ohio in 1952. Beginning about 1945, process wastes and residues were taken from the St. Louis plants and stored at a government storage site near the St. Louis Airport.
During the 24-year period (1942 to 1966), the company designed and operated feed materials facilities in St. Louis and St. Charles County,Missouri, which employed a total of about 3,300 individuals and produced more than 100,000 tons of purified natural uranium materials. The plants in St. Louis, Missouri, were constructed and operated on Mallinckrodt land. In St. Charles County, the land, buildings, and all equipment belonged to the U.S. Government.
The contractual work from 1942 to 1947 was carried out under the Manhattan Engineer District (MED) project. This contract was transferred in 1947 to the newly formed AEC and remained under the AEC New York Operations until 1954. At this time, the contract was transferred to the AEC Oak Ridge Operations and remained there until 1966, at which time the contract was terminated.
Four plants were in existence during the history of Mallinckrodt’s government contracts. All of the work from 1942 to 1945 was carried out in previously existing structures at the Main Plant and at Plant 4 in the city of St. Louis. The Main Plant was used as a refinery forU308 feed and pitchblende until 1945, at which time these operations were closed. A new refinery called Plant 6 and located at 65 Destrehan in St. Louis began operations in 1946 to process pitchblende ore and produce U02.
Additional plants began operating at the Destrehan Street location in the period 1950-51 and went under the names Plant 6E and Plant 7. Plant 6E produced uranium metal while Plant 7 was designed to produce green salt (UF4). Plant 4 operations ended at this time, and its facilities were modified to be used as a metallurgical pilot plant for development work with uranium metal. This operation continued until 1956.
*Source
DOCUMENTS
NIOSH SEC Petition Evaluation Reports
Petition 12 (Jan 1, 1942 to Dec 31, 1957)
SEC Petition Evaluation Report, Petition SEC-00012-1, Report Rev # Draft
Report Submittal Date 07-21-2004
SEC Petition Evaluation Report, SEC-00012-2, Report Rev # Draft 2
Report Submittal Date 07-21-2004
Technical Basis Documents
SC&A
ADVISORY BOARD ON RADIATION AND WORKER HEALTH
Review of NIOSH Site Profile for Mallinckrodt Chemical Co., St. Louis Downtown Site, St. Louis, MO January 31, 2005
Share this:
EEOICPA CLAIMS
If you or your parent worked any of the DOE or AWE facilities listed on this website and became ill, you may be entitled to compensation of up to $400K plus medical benefits from the US Department of Labor.
Call EEOICPA Counsel Hugh Stephens at 1-800-548-4494, email hstephens@stephensstephens.com, or fill out the form below whether or not you have already filed a claim and even if your claim has been accepted or denied.
Contact Us
"*" indicates required fields
*note: Submission of this form does not establish an attorney-client privilege.
Contact Us
Address:
2495 Main Street, Suite 442
Buffalo, New York 14214
Phone:
(716) 852-7590
Fax:
(716) 852-7599
After Hours:
(716) 208-3525
Email Us:
R. William Stephens, Esq.
R. Hugh Stephens, Esq.
Lisa P. Neff, Esq.